Corrections Dept
Eriksen Ellison Associates
206615
Design for Repair Generator Emergency
78LL0056
Emergency construction generator controls project needed design and construction administration.
Project Duration
Tue, 02/22/2022 - 00:00
Wed, 11/30/2022 - 00:00
Sat, 12/31/2022 - 00:00
Yes
{Empty}
Contract Amounts
$16000.00
$0
$16000.00
Yes
AP
Yes
Within RECS guidelines for an emergency project.
Glen Heino
glen.heino@state.mn.us
Satisfactory – The Consultant performed in an average manner that demonstrated an acceptable understanding of the owner’s requirements and contract requirements. The consultant’s overall performance is equal to any negative performance. The Consultant has contributed to the success of the project.
Satisfactory – The Consultant performed in an average manner that demonstrated an acceptable understanding of the owner’s requirements and contract requirements. The consultant’s overall performance is equal to any negative performance. The Consultant has contributed to the success of the project.
Satisfactory – The Consultant performed in an average manner that demonstrated an acceptable understanding of the owner’s requirements and contract requirements. The consultant’s overall performance is equal to any negative performance. The Consultant has contributed to the success of the project.
Satisfactory – The Consultant performed in an average manner that demonstrated an acceptable understanding of the owner’s requirements and contract requirements. The consultant’s overall performance is equal to any negative performance. The Consultant has contributed to the success of the project.
Yes
n/a
4 - satisfied