Transportation Department
Arcadis U.S., Inc.
203941
Claim Support
1048687
MN Attorney General Office requested a 3rd party analysis of the Construction Contractor's Claim and schedule which is
standard practice in these cases.
Project Duration
Fri, 11/19/2021 - 00:00
Sat, 01/31/2026 - 00:00
Sun, 11/20/2022 - 00:00
Yes
{Empty}
Contract Amounts
$98342.18
$15671.37
$114013.55
No
state funds
No
{Empty}
Yliniemi,Seth A
Seth.Yliniemi@state.mn.us
Contractor completed their final report on time in accordance with the court ordered date and mediation
The final report was of sufficient quality as to persuade the construction contractor to settle during mediation
Ultimately Arcadis went above and beyond as to provide the highest quality product they could that resulted in going over the
original budget. Discussions were had to stay within budget on multiple occasions but with the expanded scope of discovery it
was determined that they were entitled to the additional costs.
good
Yes
{Empty}
4 - satisfied