Pollution Control Agency
GHD
179406
GHD Construction Monitoring Services Haz Waste Pit Removal (FY21)
{Empty}
Construction Oversight for the WDE Hazardous Waste Pit Removal Project for FY21
Project Duration
Mon, 07/06/2020 - 00:00
Thu, 09/30/2021 - 00:00
Thu, 09/30/2021 - 00:00
Yes
{Empty}
Contract Amounts
$39888.20
{Empty}
$39888.20
Yes
State
No
{Empty}
Cliff Shierk
clifford.shierk@state.mn.us
Very Satisfied
Very Satisfied
Very Satisfied
Very Satisfied
During the duration of the project, GHD provided exceptional engineering support and construction services. The project manager communicated very well during all phases of the project and made sure that the work being performed was done to the project specifications and in the best interest of the State.
Yes
{Empty}
5 - very satisfied