Submission Number: 25000
Submission ID: 76111
Submission UUID: 5356f7d0-ff31-4a8b-9539-048988f1db5c

Created: Thu, 02/23/2023 - 15:22
Completed: Thu, 02/23/2023 - 15:22
Changed: Mon, 02/27/2023 - 16:36

Remote IP address: (unknown)
Submitted by: dalia.jorge
Language: English

Is draft: No

Locked: Yes
Transportation Department
HR Green, Inc.
193043
Intersection evaluations TH 169 and Belgrade Avenue.
1046084
The contract was necessary to delivery a final ICE report for two ramp terminal intersections. The District didn't have the
internal resources to delivery this work.
Project Duration
Fri, 05/07/2021 - 00:00
Fri, 04/29/2022 - 00:00
Wed, 08/31/2022 - 00:00
No
{Empty}
Contract Amounts
$99198.58
{Empty}
$99198.58
Yes
state funds
No
{Empty}
Benzkofer,Brett D
brett.benzkofer@state.mn.us
The contractor provided timely submittal of project deliverables, communications, and responses
The contractor provided quality work throughout the project.
The cost was appropriate for the scope of work
good
Yes
{Empty}
5 - very satisfied