Transportation Department
Moriarty Scheduling Services, LLC
158486
Grand Marais CPM Schedule
1033786
MnDOT required the construction contractor to use a CPM schedule on the Grand Marais Construction Project. This was done
to mitigate delays that could have been costly to the department. MnDOT contract admin staff lacks the technical ability to
review P6 schedules, Moriarty was contracted to assist MnDOT staff in this effort.
Project Duration
Mon, 06/03/2019 - 00:00
Mon, 05/31/2021 - 00:00
Tue, 08/31/2021 - 00:00
Yes
{Empty}
Contract Amounts
$47771.20
{Empty}
$47771.20
Yes
STATE FUNDS
No
{Empty}
Deming,Andrew
andrew.deming@state.mn.us
Moriarty responded promptly to all MnDOT's requests. Moriarty was available to MnDOT staff via cell phone if issues arose
during construction that needed to be addressed quickly.
It was immediately clear that Moriarty was a subject matter expert in CPM schedule review. They were easy to work with a
provided a major benefit to MnDOT's construction admin staff. Information provided by Moriarty was timely and professional.
When MnDOT additional requests were made, Moriarty responded in a timely manner.
In line with industry average.
GOOD
Yes
{Empty}
5 - very satisfied