Submission Number: 25083
Submission ID: 76526
Submission UUID: cf13fa27-608f-4ce2-b689-ca411f4cd50c

Created: Wed, 03/15/2023 - 14:42
Completed: Wed, 03/15/2023 - 14:42
Changed: Thu, 04/06/2023 - 14:15

Remote IP address: (unknown)
Submitted by: lee.zettler
Language: English

Is draft: No

Locked: Yes
Agriculture Dept
Terracon Consultants, Inc.
217857
Phase 18 Oversight, Phase 18 CAR, and Construction Stormwater Pollution Prevention Plan
RWA253112
The environmental contractor (Terracon Consultants, Inc.)performed oversight of the Phase XVIII Corrective Actions (soil excavation, transportation, and disposal), preparation of the Phase XVIII Corrective Action Report (CAR), and preparation of the Construction Stormwater Pollution Prevention Plan at the former Kettle River Company – Creosote Plant Site in Sandstone, Pine County, Minnesota. The work was necessary to minimize risks to human health and the environment from creosote impacts in soil and groundwater.
Project Duration
Thu, 09/01/2022 - 00:00
Fri, 06/30/2023 - 00:00
Tue, 03/14/2023 - 00:00
Yes
{Empty}
Contract Amounts
$71100.88
{Empty}
$54582.27
Yes
FY23 2801 B04311S7 B041E02 (State MERLA)
No
{Empty}
Lee Zettler
Lee.Zettler@state.mn.us
The Contractor completed the deliverables in a timely manner.
The quality of the Contractor's deliverables and services was excellent. The Contractor did an excellent job communicating to the MDA and providing recommendations for the project. The Contractor did a great job completing the Phase XVIII Corrective Action Report using GIS-based data to update the maps. The preparation of a Construction Stormwater Pollution Prevention Plan was also completed to high-standards. The Contractor provided critical oversight and important assistance to the MDA in managing the Phase XVIII Excavation.
The Contractor's costs were fair and reasonable. The Contractor did a great job consolidating tasks during mobilizations to the site and utilizing appropriate level staff for the tasks, which reduced costs to the project.
The Contractor's overall performance on the project was excellent. The Contractor did a great job working on and coordinating multiple tasks for the contract. The Contractor was always responsive to requests and communications from the MDA, and provided professional assistance and partnership to the MDA that contributed greatly to the success of the project.
Yes
{Empty}
5 - very satisfied