Submission Number: 25093
Submission ID: 76576
Submission UUID: 31133d60-8b4b-48f5-a246-02ff9d77d88e

Created: Thu, 03/16/2023 - 12:35
Completed: Thu, 03/16/2023 - 12:35
Changed: Thu, 04/06/2023 - 14:27

Remote IP address: (unknown)
Submitted by: dalia.jorge
Language: English

Is draft: No

Locked: Yes
Transportation Department
WSB & Associates, Inc
185017
Efficiencies Analysis
1044896
Legislative mandate to complete this analysis and MnDOT staff does not have the time.
Project Duration
Tue, 10/27/2020 - 00:00
Sun, 10/31/2021 - 00:00
Wed, 08/31/2022 - 00:00
Yes
{Empty}
Contract Amounts
$65729.44
$33901.98
$99631.42
Yes
state funds
No
{Empty}
Belden,Deanna Keltner
Deanna.Belden@state.mn.us
Everything was completed on time/within an appropriate window.
Excellent quality work.
Very reasonable.
good
Yes
{Empty}
5 - very satisfied