Transportation Department
University of Minnesota
148359
Criteria and Guidelines for Three-Lane Road Design and Operation
1003325W73
A 4-3 conversion involves changing a four-lane undivided road into one with two general travel lanes separated by a two-way left
turn lane. The main objective of this project was to identify conditions where 4-3 conversions might be feasible at AADTs greater
than 15,000.
Project Duration
Fri, 09/28/2018 - 00:00
Mon, 11/30/2020 - 00:00
Wed, 06/28/2023 - 00:00
No
{Empty}
Contract Amounts
$155559.00
{Empty}
$155559.00
Yes
STATE AID FUNDS
No
{Empty}
Sindt,Matthew George
Matthew.Sindt@state.mn.us
Deliverables were provided on time throughout the project.
Quality research and report. There were very few proposed edits from the advisory panel on the final report. Very well done
Project costs were in alignment with our typical research projects
GOOD
Yes
{Empty}
5 - very satisfied