Pollution Control Agency
BARR ENGINEERING CO
228029
SW-163 Barr construction oversight_FY23
{Empty}
Barr Engineering Co. will perform oversight of the new cover construction at the Brookston Closed Landfill and West Dump in Brookston, MN.
Project Duration
Wed, 04/26/2023 - 00:00
Fri, 06/30/2023 - 00:00
Fri, 06/30/2023 - 00:00
Yes
{Empty}
Contract Amounts
$127472.93
$0
$127472.93
Yes
{Empty}
No
{Empty}
Daniel Hegrenes
Daniel.Hegrenes@STATE.MN.US
VERY SATISFIED
VERY SATISFIED
VERY SATISFIED
VERY SATISFIED
Yes
{Empty}
5 - very satisfied