Submission Number: 25797
Submission ID: 80096
Submission UUID: d6e9635c-8f19-491c-8537-87a696a0c7ef

Created: Thu, 08/24/2023 - 15:19
Completed: Thu, 08/24/2023 - 15:19
Changed: Fri, 09/01/2023 - 13:57

Remote IP address: (unknown)
Submitted by: dalia.jorge
Language: English

Is draft: No

Locked: Yes
Transportation Department
WSB & Associates, Inc
186299
Right of Way Acquisition
1036831
The number of parcels on the project was to large to handle with the District staff
Project Duration
Wed, 11/25/2020 - 00:00
Fri, 06/30/2023 - 00:00
Fri, 06/30/2023 - 00:00
Yes
{Empty}
Contract Amounts
$690457.91
{Empty}
$690457.91
Yes
state funds
No
{Empty}
Bleess,Chad
Chad.Bleess@state.mn.us
Contracted was timely in communication with issues regarding parcels and getting the project activities completed on schedule.
Contractor provided excellent service to the parcel owners and to the State.
The contractor came in under budget
good
Yes
{Empty}
5 - very satisfied