Submission Number: 25865
Submission ID: 80436
Submission UUID: f4ada47b-939c-41e0-bf94-14738664b452

Created: Tue, 09/12/2023 - 18:04
Completed: Tue, 09/12/2023 - 18:04
Changed: Tue, 10/03/2023 - 13:25

Remote IP address: (unknown)
Submitted by: dalia.jorge
Language: English

Is draft: No

Locked: Yes
Transportation Department
SRF Consulting Group, Inc
226021
2023 Clearwater, Delano, St. Michael, Wadena Signal Optimization
1052874
MnDOT signal staff doesn't have the available time to conduct all the traffic counts, build all the new models, create the new timing plans and implement the plans in the field.
Project Duration
Thu, 03/16/2023 - 00:00
Fri, 06/30/2023 - 00:00
Fri, 06/30/2023 - 00:00
Yes
{Empty}
Contract Amounts
$64030.19
{Empty}
$64030.19
Yes
state fund
No
{Empty}
Fahrendorf,John Lester
John.Fahrendorf@state.mn.us
SRF completed all deliverables on time.
SRF was thorough and paid good attention to detail.
SRT's cost was fair and reasonable
good
Yes
{Empty}
5 - very satisfied