Submission Number: 25923
Submission ID: 80746
Submission UUID: b657232f-2fbf-4285-ad83-601e75e879bc

Created: Tue, 10/10/2023 - 17:52
Completed: Tue, 10/10/2023 - 17:52
Changed: Mon, 10/30/2023 - 19:18

Remote IP address: (unknown)
Submitted by: dalia.jorge
Language: English

Is draft: No

Locked: Yes
Transportation Department
Sambatek, LLC fka Sambatek, Inc
212787
FY22 Truck Station Surveys
1050755
Survey MnDOT truck stations for building projects
Project Duration
Fri, 06/03/2022 - 00:00
Sun, 11/13/2022 - 00:00
Sun, 11/13/2022 - 00:00
No
{Empty}
Contract Amounts
$99751.03
{Empty}
$99751.03
Yes
state funds
No
{Empty}
Reider,Neile John
Neile.Reider@state.mn.us
The contractor's timeliness did not meet expectations. The project experienced significant delays, resulting in an additional year of work beyond the originally planned timeline. Completing the project required substantial effort from all parties involved to ultimately bring it to completion.
The final, accepted product delivered by Sambatek met expectations, and in this regard, they deserve credit for their dedication
in seeing the project through to completion. It's important to note that the initial submittals did not meet expectations or the
contract requirements, resulting in their rejection. However, Sambatek's commitment to addressing these issues and ultimately
delivering a product that met the required standards demonstrates their dedication to quality.
The overall cost by the contractor appeared to be appropriate, with no significant issues related to cost control (costs were in
alignment with past projects).
good
Yes
{Empty}
3 - neutral