Bolton & Menk, Inc.
218267
Drainage and agricultural drainage review and analysis
1051460
We needed to hire a consulting company familiar with drainage in southern minnesota in a compressed schedule for court testimony. We needed an impartial 3rd party to evaluate the effects of a MnDOT project on adjacent drainage
Project Duration
Fri, 09/02/2022 - 00:00
Fri, 09/01/2023 - 00:00
Fri, 12/23/2022 - 00:00
Yes
{Empty}
Contract Amounts
$24975.00
{Empty}
$24975.00
Yes
state funds
No
{Empty}
DeMaster,Jared William
Jared.DeMaster@state.mn.us
The Contract did a great job of meeting an aggressive schedule.
The Contractor supplied a good quality product in the form of a hydraulic modeling report
The Contractor's costs were reasonable for the scope and schedule requirements of the Contract
good
Yes
{Empty}
4 - satisfied