Corrections Dept
EEA
231181
Design for Replace Barracks Boiler at MCF Willow River
78WR0016
Replacement of boilers at Correctional Facility in Willow River.
Project Duration
Mon, 07/03/2023 - 00:00
Mon, 02/19/2024 - 00:00
Mon, 02/19/2024 - 00:00
Yes
{Empty}
Contract Amounts
$21500.00
$920.50
$22420.50
Yes
Asset Preservation Funds
No
{Empty}
Cindy Dillahunty
cindy.dillahunty@state.mn.us
Very timely, met project milestones.
Documents were good, no change orders to construction cost.
Fair design fees.
EEA is very familiar with working with the State and thus, very familiar with our processes. This results in ease of project delivery. They work efficiently.
Yes
None.
5 - very satisfied