Pollution Control Agency
Tetra Tech
207837
Water Storage in the Minnesota River Basin Modeling
AI 191308 / PRO20220004
The contractor will work to support the science needed when planning in Minnesota for water storage practice implementation. The goal is to provide practical water storage recommendations that can be incorporated into smaller scale planning within HUC8 watersheds, as well as larger scale planning for the Sediment Reduction Strategy for the Minnesota River and South Metro Mississippi River by completing the work elements outlined below. The project will be guided through monthly virtual consultation between the consultant and MPCA technical experts, along with other experts included by the MPCA project manager or technical leads.
Project Duration
Mon, 02/21/2022 - 00:00
Thu, 05/30/2024 - 00:00
Thu, 05/30/2024 - 00:00
Yes
{Empty}
Contract Amounts
$319212.51
{Empty}
$319192.77
Yes
State
Yes
Work was able to be done under the State’s master contract for this complex model.
Bryan Spindler
bryan.spindler@state.mn.us
Very satisfied - Project deliverables, draft reports, presentations edits to draft review comments and invoices were timely.
Satisfied - New project that was complicated and cutting edge and involved inputs from many partners.
Very satisfied - Project remained with the budget. Only one amendment was needed due to staff changes. Got the work done for the money.
Very satisfied - Well done considering the staff changes that occurred during the project. Project stayed on task and made the milestone timelines. Project identified a technique to model water storage potential at different scales in the Minnesota River Basin.
Yes
None
5 - very satisfied