Transportation Department
SRF Consulting Group, Inc
203553
TH 47/65 PEL (Phase II)
1047185
The contract was necessary to complete a planning study to determine the future design of highway 47 and 65
Project Duration
Mon, 11/08/2021 - 00:00
Thu, 08/31/2023 - 00:00
Wed, 01/31/2024 - 00:00
Yes
{Empty}
Contract Amounts
$934661.18
$170976.01
$1105637.19
Yes
state funds
No
{Empty}
Bower,Christopher
Christopher.Bower@state.mn.us
Contractor submitted deliverables in a timely manner.
I note below that the project didn't finish on time, but that was due to factors outside the contractor's direct control.
Contractor generally submitted quality documents, with the exception of some ADA related issues for public facing materials
Contractor provided services in line with their budget. The overall cost of the project is high, but that is primarily due to state
requirements in the contract
good
Yes
{Empty}
4 - satisfied